The contractors Lloyd and Smith have made a good start in the first week of work. Working hard to make the church as safe and accessible as possible. Due to their
hard work the church is still able to be used for all of its usual services and will be open throughout the day as usual
The list of work completed this week is:
External and internal scaffolding completed
The chancel roof has been stripped of slates and is being prepared for the new slates.
The inner porch has been removed and the oak panels retained for use later in the project. The community area will be more useful when the work is complete.
We hope to do regular updates throughout the work. This will included regular Facebook posts, e-letters and monthly reports. If you have any questions please message us through the Facebook page.